<?xml version="1.0" encoding="UTF-8"?>
<article article-type="research-article" dtd-version="1.3" xml:lang="ru" xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:mml="http://www.w3.org/1998/Math/MathML" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="https://metafora.rcsi.science/xsd_files/journal3.xsd">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">moitvivt</journal-id>
      <journal-title-group>
        <journal-title xml:lang="ru">Моделирование, оптимизация и информационные технологии</journal-title>
        <trans-title-group xml:lang="en">
          <trans-title>Modeling, Optimization and Information Technology</trans-title>
        </trans-title-group>
      </journal-title-group>
      <issn pub-type="epub">2310-6018</issn>
      <publisher>
        <publisher-name>Издательство</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.26102/2310-6018/2025.49.2.049</article-id>
      <article-id pub-id-type="custom" custom-type="elpub">1968</article-id>
      <title-group>
        <article-title xml:lang="ru">Распределение ресурсов как основа оптимизации сетевой модели проекта</article-title>
        <trans-title-group xml:lang="en">
          <trans-title>Resource allocation as a basis for optimizing the network  model of a project</trans-title>
        </trans-title-group>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <contrib-id contrib-id-type="orcid">0000-0002-3944-2266</contrib-id>
          <name-alternatives>
            <name name-style="eastern" xml:lang="ru">
              <surname>Леденёва</surname>
              <given-names>Татьяна Михайловна</given-names>
            </name>
            <name name-style="western" xml:lang="en">
              <surname>Ledeneva</surname>
              <given-names>Tatyana Mikhailovna</given-names>
            </name>
          </name-alternatives>
          <email>ledeneva-tm@yandex.ru</email>
          <xref ref-type="aff">aff-1</xref>
        </contrib>
        <contrib contrib-type="author">
          <contrib-id contrib-id-type="orcid">0009-0000-5156-2482</contrib-id>
          <name-alternatives>
            <name name-style="eastern" xml:lang="ru">
              <surname>Шишов</surname>
              <given-names>Максим Михайлович</given-names>
            </name>
            <name name-style="western" xml:lang="en">
              <surname>Шишов</surname>
              <given-names>Максим Михайлович</given-names>
            </name>
          </name-alternatives>
          <email>m.m.shishov@mail.ru</email>
          <xref ref-type="aff">aff-2</xref>
        </contrib>
      </contrib-group>
      <aff-alternatives id="aff-1">
        <aff xml:lang="ru">Воронежский государственный университет</aff>
        <aff xml:lang="en">Voronezh State University</aff>
      </aff-alternatives>
      <aff-alternatives id="aff-2">
        <aff xml:lang="ru">Воронежский государственный университет</aff>
        <aff xml:lang="en">Voronezh State University</aff>
      </aff-alternatives>
      <pub-date pub-type="epub">
        <day>01</day>
        <month>01</month>
        <year>2026</year>
      </pub-date>
      <volume>1</volume>
      <issue>1</issue>
      <elocation-id>10.26102/2310-6018/2025.49.2.049</elocation-id>
      <permissions>
        <copyright-statement>Copyright © Авторы, 2026</copyright-statement>
        <copyright-year>2026</copyright-year>
        <license license-type="creative-commons-attribution" xlink:href="https://creativecommons.org/licenses/by/4.0/">
          <license-p>This work is licensed under a Creative Commons Attribution 4.0 International License</license-p>
        </license>
      </permissions>
      <self-uri xlink:href="https://moitvivt.ru/ru/journal/article?id=1968"/>
      <abstract xml:lang="ru">
        <p>В статье представлена процедура оптимизации проекта в форме сетевого графика. Идея оптимизации заключается в том, чтобы все пути из исходного события в завершающее сделать критическими за счет переноса ресурсов с некритических работ с ненулевым свободным резервом на критические работы некоторого критического пути. В предположении, что зависимость продолжительности работы от выделенных для ее выполнения ресурсов линейная, получены формулы для новых продолжительностей работ и нового критического времени. Перераспределение ресурсов позволяет сократить продолжительности некоторых работ, но делает проект более напряженным. Для оценки проекта с новыми продолжительностями работ для каждой работы введен коэффициент напряженности как интенсивность использования обобщенного ресурса проекта в единицу времени. В процессе оптимизации данные характеристики ведут себя по-разному, поэтому введена обобщенная характеристика интенсивности проекта на основе агрегирования частных характеристик работ с использованием принципа «нечеткого большинства». Заметим, что для агрегирования частных оценок можно использовать известные взвешенные средние, при этом для определения весов можно применить, например, метод парных сравнений. В статье приведен иллюстративный пример, демонстрирующий работу предложенного подхода.</p>
      </abstract>
      <trans-abstract xml:lang="en">
        <p>This article presents a project optimization procedure in the form of a network graph. The idea of optimization is to make all paths from the initial event to the final one critical by transferring resources from non-critical work with a non-zero free reserve to critical work of some critical path. Assuming that the dependence of the duration of work on the resources allocated for its execution is linear, formulas for new work durations and a new critical time are obtained. The reallocation of resources reduces the duration of some work, but makes the project more stressful. To evaluate a project with new work durations, a stress coefficient was introduced for each work as the intensity of use of the generalized project resource per unit of time. In the process of optimization, these characteristics behave differently, therefore, a generalized characteristic of the project intensity is introduced based on the aggregation of particular characteristics of work using the "fuzzy majority" principle. Note that well-known weighted averages can be used to aggregate partial estimates, while, for example, the method of paired comparisons can be used to determine the weights. The article provides an illustrative example demonstrating the operation of the proposed approach.</p>
      </trans-abstract>
      <kwd-group xml:lang="ru">
        <kwd>сетевой график</kwd>
        <kwd>критический путь</kwd>
        <kwd>ресурс</kwd>
        <kwd>оптимизация</kwd>
        <kwd>коэффициент напряженности</kwd>
        <kwd>агрегирование</kwd>
      </kwd-group>
      <kwd-group xml:lang="en">
        <kwd>network graph</kwd>
        <kwd>critical path</kwd>
        <kwd>resource</kwd>
        <kwd>optimization</kwd>
        <kwd>tension coefficient</kwd>
        <kwd>aggregation</kwd>
      </kwd-group>
      <funding-group>
        <funding-statement xml:lang="ru">Исследование выполнено без спонсорской поддержки.</funding-statement>
        <funding-statement xml:lang="en">The study was performed without external funding.</funding-statement>
      </funding-group>
    </article-meta>
  </front>
  <back>
    <ref-list>
      <title>References</title>
      <ref id="cit1">
        <label>1</label>
        <mixed-citation xml:lang="ru">Гельруд Я.Д., Логиновский О.В. Управление проектами: методы, модели, системы. Челябинск: Издательский центр ЮУрГУ; 2015. 331 с.</mixed-citation>
      </ref>
      <ref id="cit2">
        <label>2</label>
        <mixed-citation xml:lang="ru">Сетевые модели в управлении. Москва: Эгвес; 2011. 442 с.</mixed-citation>
      </ref>
      <ref id="cit3">
        <label>3</label>
        <mixed-citation xml:lang="ru">Зуховицкий С.И., Радчик И.А. Математические методы сетевого планирования. Москва: Наука; 1965. 296 с.</mixed-citation>
      </ref>
      <ref id="cit4">
        <label>4</label>
        <mixed-citation xml:lang="ru">Голенко-Гинзбург Д.И. Стохастические сетевые модели планирования и управления разработками. Воронеж: Научная книга; 2010. 283 с.</mixed-citation>
      </ref>
      <ref id="cit5">
        <label>5</label>
        <mixed-citation xml:lang="ru">Леденев М.Ю., Сергиенко М.А. Алгоритм расчета нечетких и интервальных оценок временных параметров сетевой модели проекта. Международный научно-исследовательский журнал. 2021;(6-1):118–128. https://doi.org/10.23670/IRJ.2021.108.6.019</mixed-citation>
      </ref>
      <ref id="cit6">
        <label>6</label>
        <mixed-citation xml:lang="ru">Леденева Т.М., Черменев Д.А. Нечеткая модель проекта с продолжительностями работ в форме обобщенных гауссовых чисел. Вестник Воронежского государственного университета. Серия: Системный анализ и информационные технологии. 2015;(2):72–81.</mixed-citation>
      </ref>
      <ref id="cit7">
        <label>7</label>
        <mixed-citation xml:lang="ru">Шашкин А.И., Ширяев М.М. Календарное планирование работ по проекту на основе нечетких исходных данных. Вестник Самарского государственного университета. Естественнонаучная серия. 2008;(3):208–216.</mixed-citation>
      </ref>
      <ref id="cit8">
        <label>8</label>
        <mixed-citation xml:lang="ru">Глушков А.Ю., Дорофеев Д.В., Моисеев С.И., Перевалова О.С. Оптимизационная математическая модель перераспределения ресурсов в управлении проектами. В сборнике: Системное моделирование социально-экономических процессов: труды 43-ой Международной научной школы-семинара, 13–18 октября 2020 года, Воронеж, Россия. Воронеж: Истоки; 2020. С. 422–426.</mixed-citation>
      </ref>
      <ref id="cit9">
        <label>9</label>
        <mixed-citation xml:lang="ru">Beliakov G., Sola H.B., Calvo T. A Practical Guide to Averaging Functions. Cham: Springer; 2016. 352 p. https://doi.org/10.1007/978-3-319-24753-3</mixed-citation>
      </ref>
      <ref id="cit10">
        <label>10</label>
        <mixed-citation xml:lang="ru">Леденева Т.М., Левкина И.Н. Обзор основных классов операторов порядкового взвешенного агрегирования. Вестник Воронежского государственного университета. Серия: Системный анализ и информационные технологии. 2022;(1):5–31. https://doi.org/10.17308/sait.2022.1/9198</mixed-citation>
      </ref>
    </ref-list>
    <fn-group>
      <fn fn-type="conflict">
        <p>The authors declare that there are no conflicts of interest present.</p>
      </fn>
    </fn-group>
  </back>
</article>